Construction-related services (№6319750)

10 feb

Number: 6319750

Country: United Kingdom

Source: TED


Link to original

To view links to the source need to register

Publication date


10-02-2018

Description


  1. Section I
    1. Name and addresses
      Derry City & Strabane District Council
      98 Strand Road
      Derry
      BT48 7NN
      United Kingdom
      Telephone: +44 2871253253
      E-mail: [email protected]
    2. Type of the contracting authority:
      Regional or local authority
    3. Main activity:
      General public services
  2. Section II
    1. Scope of the procurement:
      1. Title:

        Restricted List Application North West Cross Border Greenways


        Reference number: T ENV17-042.
      2. Main CPV code:
        71500000, 71530000, 71520000, 71541000, 71244000, 71324000, 71311000, 71312000, 71311210
      3. Type of contract:
        Services
      4. Short description:

        The North West Greenway Network (NWGN) project involves a cross-border (CB) partnership between Derry City and Strabane District Council (DCSDC), Donegal County Council (DCC), Transport NI (TNI) and Sustrans. It aims to develop up to 46.5 km of Greenway network at 3 Cross Border locations to a standard width of 3 m wide. The overall capital cost and programme activity is costed at EUR 18 500 000.

        The proposed greenway routes are as follows:

        — Route 1: Derry via Pennyburn and Bridgend border crossing to Buncrana/via Tooban Junction, 32.5 km,

        — Route 2: Muff Village to Derry via Culmore and Muff border crossing, 10.5 km,

        — Route 3: Strabane to Lifford via Lifford Bridge, 3.5 km.

        The ICT commission for this project will consist of a single contract, with the appointed ICT undertaking the design development, contract administration and project implementation of the works.


      5. Information about lots:
        This contract is divided into lots: no
      6. Total value of the procurement:
        Value excluding VAT: 495 340.00 GBP
    2. Description
      1. Title:
      2. Additional CPV code(s):
        71530000, 71520000, 71541000, 71244000, 71324000, 71311000, 71312000, 71311210
      3. Place of performance:
        Main site or place of performance:

        The service will focus on the provision of a high quality cross border greenway from Derry to Buncrana, Derry to Muff and Strabane to Lifford.


      4. Description of the procurement:

        Derry City and Strabane District Council (The Employer) seeks to appoint an Economic Operator to provide the services of an Integrated Consultant Team (ICT) to undertake the technical design and pre tender estimate, (RIBA Stage 4), and act on behalf of the employer to oversee the procurement of 2 separate IST contracts (1 for NI and 1 for RoI) and construction of the new cross border greenways, up to RIBA Stage 7.

        Working in close consultation with the Employer, the ICT will be required to provide a design that meets the strategic aims and objectives of the Council and to manage the construction of the cross border greenways within quality, budget and programme requirements.

        The Integrated Consultant Team must be capable of delivering the entire range of specialist design services including but not limited to the following disciplines:

        — Lead Consultant — any discipline,

        — Principal Designer,

        — Project Manager,

        — Civil Engineer,

        — Structural Engineer,

        — Quantity Surveyor/Cost Consultant,

        — Electrical Engineer,

        — Planning Consultant,

        — Landscape Architect,

        — Highways Engineer,

        — Legal Services — Procurement and Contract Law,

        — Environmental Engineer/Ecologist,

        — Land Valuer,

        — NEC3 Supervisor,

        — Any other consultant the Economic Operator deemed necessary to complete this commission.

        The ICT will be appointed under the NEC3 Professional Service Contract Option A based on the scope of services, subject to funding, which will be detailed in the Invitation to Tender documents.

        It is currently envisaged that the construction works carried out in Northern Ireland will be completed under a ‘Traditional Employers Design’ NEC3 Engineering and Construction Contract. The construction works that are to be carried out in the Republic of Ireland will be administered under a “Government Contracts Committee for Construction (GCCC) — PW-CF3 — Public Works Contract for Civil Engineering Works designed by the Employer” form of contract.

        The estimated capital budget for the proposed works will be in the region of EUR 18 500 000 which includes VAT, professional fees and other project development costs.

        7.2.4 Project Scope and Complexity

        Route 1 — Derry to Buncrana Greenway Project — 32.5 km.

        This route commences at Pennyburn in Derry and extends to Bridgend in Donegal at the border crossing and continues onto Buncrana via Tooban Junction and Inch. The route comprises a mix of shared use space, new route development and utilisation of disused railway lines. As part of the design development for this route DCC would like to consider options for an online and offline section between Bridgend and Fahan.

        The works along this route will include but not limited to, provision of a new 3 m wide greenway, widening existing footways to 3 m, provision of new retaining walls, pedestrian footbridges / widening of existing bridges, drainage, service diversions, land acquisition, road realignment and accommodation works.

        Route 2 — Derry to Muff Greenway Project — 10.5 km.

        This green way route links the village of Muff in Donegal to the commuter settlement of Culmore in Co. Derry, connecting to Derry City along realigned shared routes. This route will include a small connecting bridge at Bay Road which will link the new greenway network to the existing network.

        The works along this route will include but not limited to, provision of a new 3 m wide greenway, widening existing footways to 3 m, provision of new pedestrian/cycleway bridge, provision of new retaining walls, drainage, service diversions, land acquisition, road realignment and accommodation works.

        Route 3 — Strabane to Lifford — 3.5 km.

        This route connects the 2 border towns of Lifford and Strabane utilising the existing bridge that spans the River Foyle connecting the cross border link with the DCC owned building located on the Letterkenny Rd formerly in use as Army barracks.

        The works along this route will be similar to Route 1 & 2.


      5. Award criteria:
        Quality criterion - Name: Methodology — Design & Construction Excellence / Weighting: 7.5
        Quality criterion - Name: Programme / Weighting: 7.5
        Quality criterion - Name: Resources / Weighting: 7.5
        Quality criterion - Name: Cost Management / Weighting: 7.5
        Price - Weighting: 70
      6. Information about options:
        Options: no
      7. Information about European Union funds:
      8. Additional information:
  3. Section IV
    1. Description:
      1. Type of procedure:
        Restricted procedure
      2. Information about a framework agreement or a dynamic purchasing system:
      3. Information about electronic auction:
      4. Information about the Government Procurement Agreement (GPA):
        The procurement is covered by the Government Procurement Agreement: no
    2. Administrative information:
      1. Previous publication concerning this procedure:
        Notice number in the OJ S: 2017/S 088-173385
      2. Information about termination of dynamic purchasing system:
      3. Information about termination of call for competition in the form of a prior information notice:
  4. Section V
    1. Contract No: 1
      Title:

      Restricted List Application North West Cross Border Greenways


    2. Award of contract
      1. Date of conclusion of the contract: 2017-11-30
      2. Information about tenders:
        Number of tenders received: 5
        Number of tenders received from SMEs: 5
        The contract has been awarded to a group of economic operators: no
      3. Name and address of the contractor:
        McAdam Design Limited
        1c Montgomery House Castlereagh Business Park 478 Castlereagh Road
        Belfast
        BT5 6BQ
        United Kingdom
        The contractor is an SME: yes
      4. Information on value of the contract/lot (excluding VAT):

        Total value of the contract/lot: 495 340.00 GBP
      5. Information about subcontracting:

  5. Section VI
    1. Additional information
    2. Procedures for review
      1. Review body
        The High Courts of Justice of Northern Ireland
        The Royal Courts of Justice, Chichester Street
        Belfast
        BT1 3JF
        United Kingdom
      2. Body responsible for mediation procedures
        The High Courts of Justice of Northern Ireland
        The Royal Courts of Justice, Chichester Street
        Belfast
        BT1 3JF
        United Kingdom
      3. Service from which information about the review procedure may be obtained

    3. Date of dispatch of this notice
      2018-02-09